ans-As per IS 456-2000,[25-40](degree).
2. Full form of 1(one) BHK ?
ans- 1 Bed room , 1 Hall , 1 Kitchen room.
3. Volume of cement Bag (50 kg) ?
ans- 0.347 meter.q OR 1.23 CFT.
4. Expair Date of cement ?
ans- 3 months.
5. Size of hook of angle ?
ans- Hook = 10D
Angle = 135 (degree)=3d
90(degree)=2d
45(degree)=1d
6. Calculation weight of steel bar formula ?
ans- d Squre * L/162.2(where d=in mm ,L=Meter)
7. Why is foundation provided. what are types of foundation ?
ans-Foundation is provoded to distribute the load of structure in the soil.
2 types 0f foundation --shallow & deep foudation.
8-Minimum grade of concrete use in RCC ?
ans- M20.
9- Shuttering Removing time (deshuttering) ?
ans- side of wall , column & other side of beam =24 to 48 hour
-beam sofit = 7 days
-slab = 3 days
removal of props of slab
-span > 6m = 21 days
-span <=6m=14 days
10 - What are the concrete tests happening on site ?
ans- slump test , compressive strength test ,water pumicability test , water absorption test.
11- What is the unit weight of steel ?
ans- the unit weight of steel is 78.5kg/meter .q
12. Unit weight of concrete ?
ans- RCC =25 KG/meter.q
-PCC =24 kg / meter.q
13- Compressive strength of bricks ?
ans- 1st class brick =105 kg/cmsqre
-2nd class brick =70 kg/ cmsqre
-3rd class brick =125 kg/cmsqre
14- Initial setting time of cement ? = 30 min
- Final setting time of cementb ? = 90 min
15 -Curing method ?
ans- spraying ,ponding , wet covering of surface , curingb chemicals , steam curing , sprinkling.
16- What is bleeding on concrete ?
ans- Bleeding is form of segrigation , in which water comes out to the surface of concrete.
17- why we do pile foundation ?
ans - Pile foundation is adopted when the soil bearing capacity is less than 24 kn/meter q.
18- Standard height of each floor ?
ans- 3meter.
19-what is guniting ?
ans- It isb the process in which mixture of cement , sand propotion of 1:3 is shooted in concrete surface with the help of crum pressere of 2 to 3 kg/cm sq.
20- what is the least count of thedolite & compass ?
ans- Thedolite =20 sec.
- Compass = 30 min.